Modify project summary

General discussion and questions about project risk management and risk analysis software RiskyProject. Includes discussion on how to perform efficient project risk analysis using our software.

Moderator: Intaver Support

Post Reply
Expert
Posts: 7
Joined: Sun Jul 09, 2006 11:11 pm

Modify project summary

Post by Expert » Fri Jan 29, 2016 5:37 am

We want to use the Project Summary as our dashboard. Is there any way to modify it?

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Re: Modify project summary

Post by Intaver Support » Fri Jan 29, 2016 5:38 am

Most of the elements in the Project Summary are hard coded i.e. they cannot be moved or modified. However, you can modify how the charts appear. If you right click on a chart, you are given a range of options of how the chart is displayed.

These include showing the Frequency and/or Cumulative Probability. In the options: you can modify colours including colors on the left and right of the slider, showing grids, headers, or the slider, width of bars (dictates the number that can be shown). To modify chart you need to right click on the Frequency and/or Cumulative Probability plot and then then select Options.

Image
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com

Post Reply