Where do you set abbreviations for days and weeks

Post by WayneDavidson » Wed Oct 14, 2015 7:17 am

We normally enter activity durations in weeks. Where do I set this and if possible can we change it the display from “weeks” to just “w”

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Re: Where do you set abbreviations for days and weeks

Post by Intaver Support » Wed Oct 14, 2015 7:21 am

You can do this very easily in the Project Options. To Set the default time units for entering duration, go to Schedule>Settings and Options>Project Options>Duration tab and select the unit from Duration is entered in drop down list.

To modify how the units appear, go to the Project Options> Units tab. There are a series of drop-down lists that allow you to select how the units are displayed. In your case, from the Weeks dropdown list select “w”.