Re: Setting cost and duration uncertainties for multiple tas
Posted: Mon Aug 17, 2015 3:36 pm
You may assign statistical distribution for duration and fixed cost for a selected group of tasks:
1. Open the Gantt View.
2. Select a group of tasks.
3. Right-click on a Task ID.
4. Select Set Low/High Duration or Low/High Fixed Cost.
5. Enter fixed values or a coefficient to calculate Low and High duration or cost based on the Base duration or cost.
6. Select a distribution from the drop-down list.
7. Click OK to apply changes.
Low and high durations and/or fixed cost will be automatically calculated. If you already manually entered low and high values for fixed cost and duration, the procedure will overwrite these values.
1. Open the Gantt View.
2. Select a group of tasks.
3. Right-click on a Task ID.
4. Select Set Low/High Duration or Low/High Fixed Cost.
5. Enter fixed values or a coefficient to calculate Low and High duration or cost based on the Base duration or cost.
6. Select a distribution from the drop-down list.
7. Click OK to apply changes.
Low and high durations and/or fixed cost will be automatically calculated. If you already manually entered low and high values for fixed cost and duration, the procedure will overwrite these values.