Enabling low and high duration/cost for the group of tasks

Post by Fer23 » Wed Jun 12, 2013 5:45 pm

Hello,

How can can set low duration/cost for the group of task. I would like to multiply duration on 0.9 and 1.1 to get low and high durations.

Best regards,
Fer23
Project risk management, decision and risk analysis

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Re: Enabling low and high duration/cost for the group of tas

Post by Intaver Support » Wed Jun 12, 2013 5:50 pm

You assign low and high duration for the group of tasks using popup menu in any view which has task information: schedule, results of report. Here is how to do it:
http://www.intaver.com/Help4/RP_Help.ph ... Tasks.html
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com