Linking risks to multiple tasks and resources
Posted: Mon Jan 09, 2012 11:32 am
Hi
1. If i am having a risk which is affecting number of tasks/resources, how it should be assigned?
2. While defining the resources; if my hourly rate is $35 per man-hour total cost for that task is calculated by multiplying total duration for that task by the rate however that doesnt represent the real cost as the number of employees working in that activity is not included. Is there a way where it can be re-presented correctly?
3. There is a comment in the project settings that project deadline doesnt affect the deterministic calculations? I have tried changing it however the results (as presented in the project summary analysis for base, low and high end dates do change); could you please advice in how to select the optimum deadline and how to de-activate its impact on results?
4. How the sensitivity ranking can be extended? I have changed minimum sensitivity coefficient to 0 but the list is still not covering all the risks. Got about 16 risks but the ranking is only stating 3 risks?
Thanks
1. If i am having a risk which is affecting number of tasks/resources, how it should be assigned?
2. While defining the resources; if my hourly rate is $35 per man-hour total cost for that task is calculated by multiplying total duration for that task by the rate however that doesnt represent the real cost as the number of employees working in that activity is not included. Is there a way where it can be re-presented correctly?
3. There is a comment in the project settings that project deadline doesnt affect the deterministic calculations? I have tried changing it however the results (as presented in the project summary analysis for base, low and high end dates do change); could you please advice in how to select the optimum deadline and how to de-activate its impact on results?
4. How the sensitivity ranking can be extended? I have changed minimum sensitivity coefficient to 0 but the list is still not covering all the risks. Got about 16 risks but the ranking is only stating 3 risks?
Thanks