Rtgorwer
Posts: 21
Joined: Wed Jan 10, 2007 4:10 pm
Location: France

Exporting schedule

Post by Rtgorwer » Thu Feb 22, 2018 3:52 pm

How can I export risk adjusted project schedule from RiskyProject to Microsoft Project or Primavera?

bbadmin
Site Admin
Posts: 18
Joined: Tue Nov 08, 2005 8:34 pm

Re: Exporting schedule

Post by bbadmin » Thu Feb 22, 2018 3:54 pm

Project schedules are exported using the MSP xml format which is supported by Microsoft Project (2010 and later), P6, and most other 3rd party scheduling software. As part of the export process, you can define whether you would like to export the deterministic schedule or the results of the simulation for Low, Base, or High or a specified percentile. Low and High results are derived from the percentiles entered for each, in the Project Options > Calculation tab. Default values are P10 and P90. Base refers to the Mean results.

To export a risk adjusted file, from the File menu, click Export > XML. The Save dialog box opens. Navigate to the folder in which you want to save the file, type in a name in the Name box, and click Save. The Export Schedule dialog box opens. Select the result option that you want to export and click OK.

Image