Do I need to populate the register?

Moderator: Intaver Support

Do I need to populate the register?

Postby Hato » Thu Apr 26, 2012 10:26 am

Questions:
1. Is it necessary to populate the Risk Register before doing a quantitative analysis?

2.How do I view/print histograms of the quantitative analysis results? (I\'m using RiskyProject Lite)
Project manager
Hato
 
Posts: 10
Joined: Tue Jun 01, 2010 4:34 am
Location: US

Re: Do I need to populate the register?

Postby Intaver Support » Thu Apr 26, 2012 10:35 am

Simple answer is no. If you are doing a straight forward SRA using Base, Low and High estimates, you do not need to involve anything from the Risk Register.

The Lite version only provides a very simplified high level reports on the risk analysis (see the 3*3 Report). To generate histograms, cum probability, and tornado reports, you will need to try the Professional version.

Intaver Support
Intaver Support Team
Intaver Support
 
Posts: 335
Joined: Wed Nov 09, 2005 9:55 am

Re: Do I need to populate the register?

Postby Hato » Mon Dec 17, 2012 10:19 pm

Where default risk probability and outcome is comming from? I would like to set default probability equal 20% not 15%.
Project manager
Hato
 
Posts: 10
Joined: Tue Jun 01, 2010 4:34 am
Location: US

Re: Do I need to populate the register?

Postby Intaver Support » Mon Dec 17, 2012 10:20 pm

Default probability and outcome is defined in Schedule -> Options -> Risk.
Intaver Support Team
Intaver Support
 
Posts: 335
Joined: Wed Nov 09, 2005 9:55 am


Return to General Discussion and Questions re: RiskyProject

Who is online

Users browsing this forum: No registered users and 1 guest

cron