Search found 63 matches
- Sun Dec 08, 2019 3:38 pm
- Forum: Project Portfolio Risk Management
- Topic: Importing Risks from Excel
- Replies: 4
- Views: 27458
Re: Importing Risks from Excel
Is it possible to import risks to desktop version of RiskyProject professional?
- Sat Nov 30, 2019 4:56 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Spikes appearing in histograms
- Replies: 1
- Views: 19315
Spikes appearing in histograms
Need your insight into “correlation”. I have saw your video tutorial and it is evident that similar risks or different activities or separate risks to single activities can be correlated. What if only single individual risk is affecting the each activity? Results are showing spikes. Any solution?
- Thu Aug 29, 2019 3:42 pm
- Forum: Project Portfolio Risk Management
- Topic: Linking summary tasks
- Replies: 1
- Views: 18832
Linking summary tasks
Is it correct to link summary tasks?
- Thu Aug 29, 2019 3:41 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Calculating work with resource calendars
- Replies: 1
- Views: 18642
Calculating work with resource calendars
How is work being calculated for resource using resource calendars?
- Thu Aug 29, 2019 3:39 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Non Working days and Time Dependent Costs
- Replies: 1
- Views: 19278
Non Working days and Time Dependent Costs
Can I use weather calendars with non-working days when calculating resource costs?
- Tue Jul 23, 2019 4:42 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Residual risk vs Unmanageable risk
- Replies: 1
- Views: 19635
Residual risk vs Unmanageable risk
What is the difference between residual risk vs unmanageable risk?
- Thu Mar 14, 2019 1:41 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Automatically update Opportunity Matrix
- Replies: 1
- Views: 18273
Automatically update Opportunity Matrix
Is there any way to automatically update the Opportunity side of the Risk Matrix to mirror changes in the Threats side.
- Tue Feb 19, 2019 10:22 am
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Default Task Types
- Replies: 4
- Views: 28947
Re: Default Task Types
By default, RiskyProject has Fixed Units set as the Task Type. Is there a reason for this?
- Wed Feb 06, 2019 3:01 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Default Task Types
- Replies: 4
- Views: 28947
Default Task Types
Can you set a default task type?
- Tue Apr 17, 2018 9:43 am
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: EVM indicators in RiskyProject
- Replies: 1
- Views: 19218
EVM indicators in RiskyProject
Does RiskyProject calculate EVM indicators?
- Mon Feb 05, 2018 10:32 am
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Launching 3rd Party tools from RiskyProject
- Replies: 1
- Views: 16948
Launching 3rd Party tools from RiskyProject
How can I include more items to File -> Launch.
- Thu Nov 23, 2017 11:05 am
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Risk is 100% mitigated
- Replies: 1
- Views: 17961
Risk is 100% mitigated
Is there any way to specify that risks which are mitigated 100% by the mitigation plan should not be used in the calculation?
- Fri Oct 13, 2017 3:31 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Instructor licenses
- Replies: 1
- Views: 11522
Instructor licenses
I am planning to teach simulations for projects in my new curriculum. How does your University Relations program work?
- Tue Jul 04, 2017 4:12 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Weather calendar
- Replies: 2
- Views: 21815
Weather calendar
What is the difference between a weather calendar and probabilistic calendar?
- Tue Jul 04, 2017 4:11 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Modifying rows and columns in the Risk Register
- Replies: 1
- Views: 11591
Modifying rows and columns in the Risk Register
How I can change size of rows in Risk Register and save column layout?