Sun Jul 15, 2007 4:31 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Low, base and high resource allocation
Replies: 3
Views: 22531

RiskyProject does not present statistical distribution associated with resource allocation. However you may view low, base, and high estimates for resources using resource view. Use checkboxes on the right pane of the view to select low, base, or high resource allocation charts. You can select four ...
by Intaver Support
Fri Jul 06, 2007 6:06 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Microsoft Project MPP file
Replies: 5
Views: 29264

RiskyProject supports MPP files created by MS Project 2000, 2002, 2003 and 2007. Most likely you have your MPP file opened by MS Project when you tried to read it in RiskyProject. Please close MS Project and try to open MPP file by RiskyProject.
by Intaver Support
Sun Jun 24, 2007 7:36 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Project decision analysis books
Replies: 5
Views: 30582

Here is a list of book we compiled: Decision Analysis Including Psychology of Judgment and Decision Making: Bell, D.E., Schleifer, A., Jr., Decision Making Under Uncertainty, Course Technology, Inc., Cambridge, MA, 1995 Clemen, R. T., Making Hard Decisions, Brooks/Cole Publishing Company, 2nd ed., P...
by Intaver Support
Sun Jun 24, 2007 7:31 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: RiskyProject 2.1 new features
Replies: 1
Views: 16655

Here is few features of RiskyProject 2.1 1. RiskyProject can now open Microsoft Project MPP file (RiskyProject Professional only). Just go to File -> Open and select MPP file format. 2. Local risk views: Local risks views help to assign risks to one or many tasks or resources. 3. Improved calendars:...
by Intaver Support
Sun Jun 24, 2007 7:30 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: RiskyProject 2.1
Replies: 4
Views: 23499

RiskyProject 2.1 can be installed together with previous versions of RiskyProject (uninstall does not required). All current users of RiskyProject can upgrade the software free of charge. RiskyProject Lite and Professional 2.1 will use license of previous RiskyProject versions. You may download Risk...
by Intaver Support
Thu Jun 07, 2007 4:43 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Printing frequency diagrams
Replies: 1
Views: 16926

You can print frequency and cumulative probability diagrams for complete project when you click on Print in Project summary.

You may also save chart to clipboard. To do it right click on the chart and select format you want to use. Then you may paste this chart to your PowerPoint presentation.
by Intaver Support
Thu Jun 07, 2007 4:39 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: ECM and CPM
Replies: 4
Views: 25507

Event chain methodology is based on CPM and Monte Carlo simulation. It also includes a number of other principles which simplify modeling uncertainties in project schedules and make it much more accurate. Among such principles: a. Analysis of the moment of the risk b. Managing chain of events c. Eve...
by Intaver Support
Tue May 08, 2007 2:50 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Critical chain
Replies: 1
Views: 17350

We consider Event chain methodology as a next step beyond Critical chain. Event chain methodology is uncertainty modeling and schedule network analysis technique, which focuses on managing events and event chains in the project schedule. Here is how our clients are using Event chain methodology: 1. ...
by Intaver Support
Tue May 08, 2007 2:36 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: New RiskyProject version
Replies: 1
Views: 19040

Here is the list of new features of RiskyProject 2.1: 1. Ability to open Microsoft Project MPP file (only for RiskyProject professional) 2. Improved probabilistic and conditional branching 3. Improved calculation performance 4. Full compatibility with Microsoft Vista 5. Improved calendars 6. Local r...
by Intaver Support
Tue May 01, 2007 6:32 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Primavera P5/RiskyProject integration
Replies: 4
Views: 27065

In order to use RiskyProject with Primavera to need to export Primavera data to MPX or Microsoft Project XML formats. Please note, that in order to export data to Microsoft Project XML you must have MS Project installed on the same computer as Primavera. Then you can import MPX or XML file to RiskyP...
by Intaver Support
Tue May 01, 2007 6:20 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Event cost
Replies: 1
Views: 19483

Event cost is not currently calculated by RiskyProject however, we are planning to implement it next releases. We agree that event cost would be very good indicator of criticality of each event. It will be calculated based on correlation coefficient associated with cost of task and cost of project.
by Intaver Support
Fri Apr 13, 2007 10:39 am
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Monte Carlo for Event Chain Methodology
Replies: 1
Views: 20664

Monte Carlo simulation is used in Event chain methodology to perform analysis of project schedules. Once events and event chains are defined, quantitative analysis using Monte Carlo simulation can be performed to quantify the cumulative impact of the events. Probabilities and impacts of risks are us...
by Intaver Support
Mon Apr 09, 2007 11:54 am
Forum: RiskyProject: Project risk management and risk analysis software
Topic: New version of RiskyProject
Replies: 1
Views: 19823

Next version of RiskyProject 2.2 supposes to be released in next couple of weeks. New features will include: 1. Support native Microsoft Project MPP file format 2. Improved integration with Microsoft Project 2007 3. Improved visualization of probabilistic and conditional branching 4. Local risk view...
by Intaver Support
Mon Apr 09, 2007 11:43 am
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: RiskyProject and VISTA
Replies: 3
Views: 23844

We are happy to let you know, that RiskyProject 2.0 is fully compatible with Microsoft Windows Vista. We have extensively tested our software with different versions of Microsoft Windows Vista and did not find any problems and conflicts.
by Intaver Support
Mon Apr 09, 2007 11:37 am
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: MPX Export to MS Project 2007
Replies: 2
Views: 20616

Yes, MSP2007 and early versions of MS Project process MPX file slightly different. We are currently in the process of releasing new version for RiskyProject 2.1. It should fully support Microsoft Project 2007. This version should be available within next couple of weeks.