Search found 995 matches

by Intaver Support
Fri Feb 13, 2009 8:09 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: New features
Replies: 18
Views: 74854

RiskyProject 3 is designed for such types of analysis. We apply methodology derived from Analytical Hierarchy Process (AHP). We perform pair-wise comparison. This way we determine weight for each risk. For example, if there is a safety risk and cost risk you may enter that safety is 4 times more imp...
by Intaver Support
Thu Jan 08, 2009 7:43 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: How to see Event Chain Diagram?
Replies: 9
Views: 41682

You may now see event chain diagrams in RiskyProject version 3 beta.
by Intaver Support
Thu Jan 08, 2009 7:42 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Import new schedule from MS Project and keep risks
Replies: 2
Views: 16963

You may do it using File -> Import ->Import XML instead of File -> Open. 1. Open your old file in RiskyProject with assigned risks 2. Click on File -> Import 3. Select that you want to keep risks 4. Click OK RiskyProject would keep risks assigned to tasks based on unique task ID from MS Project. Whe...
by Intaver Support
Fri Dec 19, 2008 5:00 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: New features
Replies: 18
Views: 74854

Intaver Institute Inc. released RiskyProject version 3. RiskyProject 3 includes the following features: - Risk register: manage threats, opportunities, and issues using fully searchable risk register - Analysis of multiple risk mitigation plans: select what plan would be most effective in your proje...
by Intaver Support
Thu Nov 27, 2008 4:04 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: How to see Event Chain Diagram?
Replies: 9
Views: 41682

We recently posted a presentation regarding RiskyProject 3. You can find a slide with event chain diagram at: http://www.intaver.com/riskyproject_presentations.html. You would see arrows associated with risks (down) and opportunities (up).
by Intaver Support
Thu Nov 27, 2008 4:01 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Academic License
Replies: 5
Views: 29758

We issue free academic license only for educational institutions, such as colleges and universities. In your case you need to purchase a full license.
by Intaver Support
Tue Nov 18, 2008 1:17 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: New features
Replies: 18
Views: 74854

RiskyProject alpha version was release November 10, 2008. Please visit: http://www.intaver.com/riskyproject_presentations.html for the preview of RiskyProject 3 new features. RiskyProject 3 Beta will be released November 28, 2008.
by Intaver Support
Tue Nov 18, 2008 4:05 am
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Low, base and high resource allocation
Replies: 3
Views: 22521

Low, base and high resource allocation is calculated based on low, base, and high results of project schedule analysis. For example, the resource is assigned to the task with the uncertain duration. Low resource allocation would correspond with low task duration (P10).
by Intaver Support
Tue Nov 18, 2008 4:01 am
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Distribution for the moment of risk
Replies: 1
Views: 15370

You can specify statistical distribution for the moment of risk. It has nothing to do with probability of risk occurrence. Statistical distribution for the moment of risk specifies time when the risk would occur during the course of task (in percents). For example, uniform distribution means with st...
by Intaver Support
Sat Oct 18, 2008 11:06 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Risk correlations
Replies: 13
Views: 52189

Strong correlation between different risks in most real life project is quite sufficient. For example you have risk "Change requirements". This risk would be strong correlated with risk "Budgetary Problems". Please remember, that correlation does not mean causation. "Change requirements" would not c...
by Intaver Support
Sat Oct 18, 2008 11:01 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Risk Mitigation Tab
Replies: 9
Views: 41955

Let's assume that you have one task 10 days duration and two risks: 1. Increase duration on 20% chance 30% 2. Increase duration on 20% chance 50% You frequency chart would have 3 spikes: 1. 10 days (no risks) 2. 12 days (risk 2 or risk 1) 4. 14 days (both risk 1 and risk 2) In some cases you don't w...
by Intaver Support
Wed Aug 27, 2008 5:21 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Distribution
Replies: 7
Views: 34716

Most likely your task has predecessors. You cannot assign the distribution for start time for the task with predecessors.
by Intaver Support
Fri Aug 22, 2008 3:54 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Risk correlations
Replies: 13
Views: 52189

We did not implement different correlation coefficient simply because our client did not ask about it. However we are planning to implement it next year in RiskyProject 4.
by Intaver Support
Fri Aug 22, 2008 3:49 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Importing MS Project data
Replies: 7
Views: 32891

MPP is proprietaries file by Microsoft. We are using third party component to read data from MPP file. Sometimes Microsoft make changes to MPP file specification for the specific data. Most likely it happened in your case. So far with RiskyProject 2.x we had only two issues related to reading data f...
by Intaver Support
Fri Aug 22, 2008 3:42 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Importing MS Project data
Replies: 7
Views: 32891

I opened very many MS Project schedules (MPP file) in RiskyProject and did not have any problems. But recently I tried to open the schedule and got a message 'Invalid file format' or something like this. Then I tried to export MS Project schedule in XML format, and did not have problems. What is wro...