Search found 998 matches

by Intaver Support
Sat Oct 08, 2022 8:17 pm
Forum: Project Portfolio Risk Management
Topic: Sorting and Filtering columns
Replies: 1
Views: 11419

Re: Sorting and Filtering columns

With latest updates of RiskyProject, sorting and filtering columns is now available. On the top of each column there is a down arrow, that allows you to sort/filter based on the data.

Image
by Intaver Support
Sat Oct 08, 2022 8:08 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: License already activated message
Replies: 1
Views: 11155

Re: License already activated message

You are most likely seeing this as you have previously activated the license on another computer. RiskyProject desktop software is a perpetual license that is associated with a license key. Under the End User License Agreement, the license can only be activated on one computer, unless dispensation i...
by Intaver Support
Sat Oct 08, 2022 7:05 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Trial period extension
Replies: 1
Views: 12289

Re: Trial period extension

Yes, upon request we can provide an extended evaluation license that will allow you to complete your evaluation of the software. Contact support@intaver.com and request an extended evaluation license.
by Intaver Support
Wed Aug 03, 2022 3:23 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Criticality Index
Replies: 1
Views: 11986

Re: Criticality Index

1. Turn on the critical path calculation. This will impact performance as CP requires both a forward and backward pass through the schedule. Here is how to do this RiskyProject Help Content (intaver.com) 2. Add the criticality index column to the Result Gantt view. https://www.intaver.com/images/PR_...
by Intaver Support
Wed Aug 03, 2022 3:18 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Start as late as possible constraint
Replies: 1
Views: 9357

Re: Start as late as possible constraint

Start as late as possible are used for a variety of management purposes, but are not used in SRA best practices. While I cannot comment on their use in your schedule usually they are used to model late procurement (pay as late as possible), but they should not be on the critical path. We have a simi...
by Intaver Support
Wed Aug 03, 2022 3:18 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: RiskyProject fails to launch after upgrade to 7.2
Replies: 1
Views: 10433

Re: RiskyProject fails to launch after upgrade to 7.2

Most likely this is a registry issue. The IT update probably corrupted the registry entry for RiskyProejct. You can reset the registry by deleting the RiskyProject registry entry. 1. To open the registry editor, press the Windows key and type “regedit” in the Search field. 2. Launch the Registry Edi...
by Intaver Support
Fri Jun 17, 2022 12:21 pm
Forum: Project Portfolio Risk Management
Topic: Edit or modify the Risk Dashboard
Replies: 1
Views: 14586

Re: Edit or modify the Risk Dashboard

To start with an empty dashboard, right click on the dashboard and click Clear Dashboard. https://www.intaver.com/images/RP_Forum_RiskDashboard1.png However, it can be useful to reuse some of the existing elements. In this case, you may want do a comparison between the current dashboard and your tem...
by Intaver Support
Fri Jun 17, 2022 12:13 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Visualizing Multiple Baselines
Replies: 1
Views: 15234

Re: Visualizing Multiple Baselines

The issue is that you can create baselines with and without the results of the analysis. If the results of the simulation are not saved with the baseline, the baseline will not appear as a cumulative probability plot. When you create a baseline, the procedure must be followed exactly to save the res...
by Intaver Support
Tue May 17, 2022 11:26 am
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Customizing Uncertainty Bands
Replies: 1
Views: 11855

Re: Customizing Uncertainty Bands

You are correct, uncertainty bands to calculate Low, Most Likely, and High durations and costs for activities based on your assessments of the inherent risk that tasks have. The dialog that allows you to modify the uncertainty bands is located on the Risk tab > Distribution group. 1. Click the Uncer...
by Intaver Support
Tue May 17, 2022 11:21 am
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Large master schedule
Replies: 1
Views: 14642

Re: Large master schedule

Without using a 3rd party tool such as MS Project that support master schedules, you have a couple of options 1. Create simplified models of each project as subtasks in a program schedule. For example each project could be rolled up to level 3 activities. You would then apply risks and uncertainties...
by Intaver Support
Wed May 04, 2022 12:12 pm
Forum: Project Portfolio Risk Management
Topic: RiskyProject Enterprise 7.2
Replies: 0
Views: 20084

RiskyProject Enterprise 7.2

Intaver Institute released new version of RiskyProject Enterprise software. RiskyProject Enterprise 7.2 is a major release which includes the following new features: 1. New Risk Dashboard: present hundreds of different key performance indicators (KPIs) and charts related to your risks with a fully c...
by Intaver Support
Wed May 04, 2022 12:09 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: RiskyProject 7.2 is released
Replies: 0
Views: 20905

RiskyProject 7.2 is released

Intaver Institute released new version of RiskyProject software. RiskyProject 7.2 is a major release which includes the following new features: 1. New Risk Dashboard: present hundreds of different key performance indicators (KPIs) and charts related to your risks with a fully customizable Risk Dashb...
by Intaver Support
Mon Mar 14, 2022 8:07 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Isolating impact of Risk Events and Uncertainties
Replies: 1
Views: 12464

Re: Isolating impact of Risk Events and Uncertainties

To Isolate the impacts of uncertainties you can disable all risks in the Risk ribbon. https://www.intaver.com/images/RP_Forum_RibbonUncertainties.png To isolate the impact of uncertainties is more difficult. I would recommend making a copy of the file and then in the Project view, select all the act...
by Intaver Support
Mon Mar 14, 2022 8:03 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Windows 11 Compatibility
Replies: 1
Views: 13350

Re: Windows 11 Compatibility

Yes, all versions of RiskyProject (Lite, Professional, and Enterprise) are compatible with Windows 11.
by Intaver Support
Fri Jan 28, 2022 9:54 am
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Post-mitigation impact calculation
Replies: 1
Views: 13281

Re: Post-mitigation impact calculation

RiskyProject takes post-mitigation probability, impacts and scores shown in Risk Register from Waterfall tab of Risk Information dialog. It is the last line, or last mitigation plan, defined by user. Risk register can also display post-mitigation probabilities, impacts and scores for individual cate...