Search found 23 matches
- Fri Jan 12, 2018 6:03 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Stat::Fit
- Replies: 1
- Views: 11739
Stat::Fit
How to use stat::fit and RiskyProject for distribution fitting?
- Wed Jan 13, 2016 11:48 am
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: How are original and actuals estimates handled?
- Replies: 1
- Views: 11382
How are original and actuals estimates handled?
How are the lo/base/hi duration values related to full duration vs remaining duration? I presume it is these values that are passed to the simulation engine. Are there other dependencies that I would need to account for?
- Mon Nov 09, 2015 10:22 am
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Is there any high level register summary
- Replies: 1
- Views: 11093
Is there any high level register summary
Is there a quick way to see a summary of the risk register. Like how many risks, what is the cost of the risks etc.
- Thu Oct 22, 2015 3:53 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Addin not calculating low and high correctly
- Replies: 1
- Views: 9395
Addin not calculating low and high correctly
Hello, we are trying to use the RiskyProject Addin in Microsoft Project, but are getting strange results for pessimistic (high) results when we run a Monte Carlo schedule risk analysis. We are using Duration1 and Duration2 for low and high durations.
- Wed Sep 09, 2015 10:50 am
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Why is there a difference in my risk assignment view
- Replies: 1
- Views: 8772
Why is there a difference in my risk assignment view
We have several projects in planning and we noticed that in on project, the risk assignment had only one Outcome, but in another it has Low, Outcome, and High fields. What is going on?
- Wed Sep 09, 2015 10:49 am
- Forum: Project Portfolio Risk Management
- Topic: Uncertainty to non-critical tasks for portfolio analysis
- Replies: 1
- Views: 9335
Uncertainty to non-critical tasks for portfolio analysis
Do I need to add uncertainty to non-critical tasks? Typically we need to run Monte Carlo schedule risk analysis on large projects. In the past, for simplicity, we have only assigned uncertainties to activities on the critical path. I saw a presentation recently that advised that we need to assign un...
- Wed Jan 02, 2008 4:19 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: RiskyProject for cost analysis
- Replies: 7
- Views: 31881
- Wed Jan 02, 2008 4:04 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: RiskyProject for cost analysis
- Replies: 7
- Views: 31881
RiskyProject for cost analysis
Hello,
I'm trying to perform cost estimation for the construction project with risks and uncertainties. I have certain events with their probabilities and outcomes, which affect cost of my project. How can I use RiskyProject to model these uncertainties?
I'm trying to perform cost estimation for the construction project with risks and uncertainties. I have certain events with their probabilities and outcomes, which affect cost of my project. How can I use RiskyProject to model these uncertainties?