Search found 995 matches

by Intaver Support
Sat Sep 19, 2009 9:23 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Negative cost and rate
Replies: 3
Views: 18453

You cannot enter negative fixed cost and rate for resource in RiskyProject directly. RiskyProject has special fields for income. If you enter income, cost will be show as negative and income will be shows positive on cash flow charts. If you use Microsoft Project schedule in RiskyProject negative ra...
by Intaver Support
Fri Sep 18, 2009 5:00 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: How to see Event Chain Diagram?
Replies: 9
Views: 41700

For more information about implementation of Event Chain Diagrams in RiskyProject please visit: http://www.intaver.com/Help3/RP3_Help_RiskAssignmentsGanttChart.html Colors represent the calculated the impact of the risk on all project parameters combined. The size of the arrow represents probability...
by Intaver Support
Thu Sep 17, 2009 11:48 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Academic License
Replies: 5
Views: 29804

We issue temporary licenses (up to 90 days) for students. Please contact us and tell us how many students are involved in your course. We will issue a temporary license for these students. It will be one license number for all students, but it can be used on multiple computers at the same time.
by Intaver Support
Fri Aug 21, 2009 3:03 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Import new schedule from MS Project and keep risks
Replies: 2
Views: 16988

RiskyProject 3 now offer a seemless integration with Microsoft Project. When RiskyProject is installed it checks if Project is installed on the computer and adds a RiskyProject toolbar and macro to Project. Using this toolbar you may transfer your project schedule to RiskyProject, add risks and unce...
by Intaver Support
Sat Aug 15, 2009 10:21 am
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Microsoft Project MPP file
Replies: 5
Views: 29273

Intaver Institute has release RiskyProject 3.2 seamlessly integrated with Project 2003 and higher. When RiskyProject is installed it checks if Project is installed on the computer and adds a RiskyProject toolbar and macro to Project. Using this toolbar you may transfer your project schedule to Risky...
by Intaver Support
Fri Jul 24, 2009 8:53 am
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Risk correlations
Replies: 13
Views: 52413

No. Each risk assignment is completely independent. For example risk "Budgetary Problems" can be assigned to task Development and task Implementation. But if "Budgetary problems" occur during development it does no mean that it will occur during Implementation. On order to correlate risk assigned to...
by Intaver Support
Fri Jun 19, 2009 11:15 am
Forum: RiskyProject: Project risk management and risk analysis software
Topic: How are risk probabilities, impacts, and scores calculated?
Replies: 4
Views: 24172

Here is an important note regarding the difference between chance of occurence and probability in RiskyProject: Chance of occurence: Chance that the selected risk, assigned to the task or resource or particular risk alternative would occur. In this document, chance of risk occurrence usually refers ...
by Intaver Support
Thu Jun 11, 2009 2:16 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Sharing Risk Register
Replies: 2
Views: 15917

You may save Risk Register to the file using Risk -> Save Risk Register. After this you may load risk register using Risk -> Load Risk Register. Risk Register can be saved on the server therefore multiple user can access it. RiskyProject offers the locking mechanism: if two users change Risk Registe...
by Intaver Support
Sat May 23, 2009 1:15 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: How are risk probabilities, impacts, and scores calculated?
Replies: 4
Views: 24172

Risk probabilities, impacts, and scores are calculated the following way: • RiskyProject tracks the impact of each risk on different project parameters for each iteration of a Monte Carlo simulation. This is done using absolute units. For example, in the first iteration Risk A caused a delay of 2 da...
by Intaver Support
Thu May 14, 2009 3:20 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: New features
Replies: 18
Views: 75010

Here is link to RiskyProject online help system. It includes detailed description of all new features of RiskyProject 3:

for RiskyProject Professional:
http://www.intaver.com/Help3/RP3_Help_Content.html

for RiskyProject Lite:
http://www.intaver.com/Help3/RP3_HelpLite_Content.html
by Intaver Support
Thu May 14, 2009 3:07 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Importing MS Project data
Replies: 7
Views: 32926

RiskyProject 2.1 did not support different resource calendar. However RiskyProject 3.1 was data model very similar to Microsoft Project. It has task calendar, resource calendar, and project calendar. You can download new version RiskyProject 3.1 from http://www.intaver.com/index-downloads.html You m...
by Intaver Support
Thu Apr 16, 2009 10:15 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: New features
Replies: 18
Views: 75010

RiskyProject 3.1 is released

RiskyProject 3 is released April 14, 2009. Here is a description of some new features: Non-schedule risks and user-defined risks outcomes RiskyProject 3 performs quantitative risk analysis on any types of risks outcomes including non-schedule risks. Non-schedule risk are risks that are not related t...
by Intaver Support
Wed Apr 01, 2009 12:39 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Duration convergence affecting Cost Validity?
Replies: 1
Views: 15216

We recommend creating one task and assign multiple risks, related to cost to this task. If you are using fixed cost increase risks, you need to define some fixed cost for this task. In RiskyProject 2.1 by default number of simulation will be 100. It may be insufficient, therefore to may go to Tools ...
by Intaver Support
Mon Mar 09, 2009 8:07 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Implementation of event chain methodology
Replies: 4
Views: 26840

RiskyProject 3 has new features directly related to Event Chain Methodology: 1. Event chain diagrams, which present threats and opportunities with their probabilities and impact. 2. None-schedule risks: safety, environment, technology, quality, etc. 3. Ability to rank all risks (schedule and non-sch...
by Intaver Support
Mon Mar 09, 2009 7:59 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Import risks from MS Acess
Replies: 1
Views: 14296

RiskyProject does not include standard tools to read data from Access database. RiskyProject currently can read data only from WelcomRisk database (Microsoft SQL Server or Oracle DB). However our rapid response team implements adapters which can read risk data from any databases. Most adapters are v...