Search found 66 matches
- Fri Dec 19, 2014 3:54 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Export results
- Replies: 1
- Views: 18570
Export results
I would like to export results of statistical analysis (raw data of Monte Carlo simulations) to Excel. How can I do it?
- Fri Dec 19, 2014 3:53 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Monte Carlo simulation results
- Replies: 1
- Views: 17157
Monte Carlo simulation results
Hello,
I was using RiskyProject 6 and then I installed RiskyProject 6.1. The results on Monte Carlo simulations for the same file are a little bit different, may be 0.1% or so. It is related to all statistical parameters and raw data. Why does it happen?
I was using RiskyProject 6 and then I installed RiskyProject 6.1. The results on Monte Carlo simulations for the same file are a little bit different, may be 0.1% or so. It is related to all statistical parameters and raw data. Why does it happen?
- Tue Jul 15, 2014 12:55 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Probabilistic risk outcome
- Replies: 1
- Views: 18284
Probabilistic risk outcome
Hello,
I have a risk which have outcome fixed delay. We have a statistical distribution for this delay. It is a triangular distribution:
- low 4 days
- most likely 7 days
- high 11 days
How can we model in in RiskyProject?
I have a risk which have outcome fixed delay. We have a statistical distribution for this delay. It is a triangular distribution:
- low 4 days
- most likely 7 days
- high 11 days
How can we model in in RiskyProject?
- Tue Jul 15, 2014 12:53 pm
- Forum: Project Portfolio Risk Management
- Topic: Licensing options for RiskyProject Enterprise
- Replies: 1
- Views: 16505
Licensing options for RiskyProject Enterprise
We already have around 20 licenses of RiskyProject Professional version 6. How can we add enterprise risk management capabilities to existing licenses?
- Mon Jun 16, 2014 4:40 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Correlation coefficient and impact
- Replies: 5
- Views: 40627
Re: Correlation coefficient and impact
I tried to perform analysis of a small schedule with two tasks. Each task has one risk assigned to it. I did it with and without correlations. I found that results are very close. Do you have similar results?
- Wed Nov 06, 2013 6:00 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Defining Event Chain
- Replies: 6
- Views: 42962
Re: Defining Event Chain
If I assign the same risk to different tasks or resources, are these assignments correlated?
- Tue Oct 15, 2013 5:33 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Default value for risk outcome
- Replies: 1
- Views: 19677
Default value for risk outcome
How can I change a default value for risk outcome? It is currently 30%. However this value should be different for different risks.
- Mon Jun 24, 2013 4:27 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: How qualitative risk impacts and scores are calculated?
- Replies: 2
- Views: 45000
Re: How qualitative risk impacts and scores are calculated?
Does RiskyProject use different algorithm for risk score calculation for duration, cost, and other risk categories?
- Thu May 16, 2013 11:42 am
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Risk arrow with risk properties
- Replies: 1
- Views: 18714
Risk arrow with risk properties
Is it possible to click on risk arrow within event chain diagram to view risk properties?
- Thu May 16, 2013 11:40 am
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: RiskyProject risk form
- Replies: 5
- Views: 36981
Search risk register
I created a custom risk property: "Material requirements". Is it possible to search risk register register to find all risks, where material requirements is greater then from example $5000?
- Sun Apr 07, 2013 6:05 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Scatter Plot in RiskyProject
- Replies: 5
- Views: 36168
Re: Scatter Plot in RiskyProject
Is is possible to insert Scatter Plot to the report, generated in Statistics report view?
- Thu Jan 03, 2013 8:29 am
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Event chain in RiskyProject
- Replies: 3
- Views: 36865
Re: Event chain in RiskyProject
I want to define correlations between risks. How to do it?
- Thu Nov 15, 2012 2:48 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: RiskyProject risk form
- Replies: 5
- Views: 36981
Re: RiskyProject 4.2 risk form
I downloaded RiskyProject 5. It has a lot of nice features. Thanks. What I would like to do is to define action items for mitigation plans and be able to report in it. How to do it RiskyProject 5?
- Thu Nov 08, 2012 4:47 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Scatter Plot in RiskyProject
- Replies: 5
- Views: 36168
Re: Scatter Plot in RiskyProject
Can I access Scatter Plol from Microsoft Project addin, the same way as I do with sensitivity chart and frequency chart?
- Thu Nov 08, 2012 4:45 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Version 5 released
- Replies: 6
- Views: 41127
Re: Version 5 released
I saw PowerPoint export in new RiskyProject. It looks great but it looks like I can exports Statistic Report only. Can I export other reports, such as cost report? We need to present cost chart as part of our PowerPoint report.