Search found 850 matches

by Intaver Support
Wed Feb 06, 2019 3:06 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Default Task Types
Replies: 4
Views: 2511

Re: Default Task Types

Yes. In the Project Options > Duration tab you an set the default Task Type. If you do not manually change this default setting, the Task Type is set to Fixed Units.

Image
by Intaver Support
Fri Jan 11, 2019 2:32 pm
Forum: Project Portfolio Risk Management
Topic: Impact of estimate quality on risk assessments
Replies: 1
Views: 1274

Re: Impact of estimate quality on risk assessments

In of themselves, the quality or accuracy of your cost and schedule estimates are a major risk a does not matter whether you are performing Monte Carlo or Critical Path analysis. The quality of any analysis is dependent upon the quality or accuracy of the inputs or as more commonly known Garbage In ...
by Intaver Support
Fri Jan 11, 2019 2:24 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Agile and schedule risk analysis
Replies: 1
Views: 1411

Re: Agile and schedule risk analysis

1. It is possible to model Agile projects in RiskyProject, however it does take some adjustment in the methodology and process. 2. Agile has iterations and storyboards which represent the steps (iterations) and deliverables (storyboards) 3. In RiskyProject you can model iterations as activities. Sto...
by Intaver Support
Fri Jan 11, 2019 2:19 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Opportunity Risk Matrix
Replies: 5
Views: 5748

Re: Opportunity Risk Matrix

Here are a couple of trends that we have seen emerge over the past years that are becoming more popular. Black Swan Risk In this case, the default risk matrix setting is used, but the Critical risk cells are extended down to the bottom right corner of the matrix. This is done so that any risks that ...
by Intaver Support
Wed Dec 26, 2018 1:08 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Opportunity Risk Matrix
Replies: 5
Views: 5748

Re: Opportunity Risk Matrix

There are no limits to the number of colors or the range of colors that you can apply to the risk matrix. As an example, if you had a standard 5x5 matrix with 25 cells, you could have 25 different colors. We don’t recommend this, but it is becoming very common to see risk matrixes with up to 6 color...
by Intaver Support
Wed Dec 26, 2018 1:01 pm
Forum: Project Portfolio Risk Management
Topic: Customized risk matrix settings for different users
Replies: 3
Views: 3390

Re: Customized risk matrix settings for different users

The Risk Trends reports can be modified using the Risk Trend Chart Settings in the Format Risk Matrix dialog box. By default, the Risk Trends provides the number of risks in each risk severity category over a designated number of periods. The periods can be set using the Risk Trend Chart periodicity...
by Intaver Support
Wed Dec 26, 2018 12:55 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Modifying Risk Matrix colors
Replies: 3
Views: 3167

Re: Modifying Risk Matrix colors

The Risk Matrix Reports are the Risk Matrix, Risk History, Risk Trends, and Risk Monitor. All are providing slightly different information on both historical and current assessment of your project risks. The Risk Matrix report allows you to show the original and post mitigated assessments for each r...
by Intaver Support
Tue Dec 11, 2018 2:15 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Reference Class estimating
Replies: 1
Views: 1862

Re: Reference Class estimating

Reference class estimating, also called reference class forecasting, is a method that uses the data from previous similar project or tasks to establish a probability distribution that can be the basis for forecasting he planned activities or project. The use of this historical data provides strong e...
by Intaver Support
Tue Dec 11, 2018 2:13 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Cost Type Resources
Replies: 1
Views: 1844

Re: Cost Type Resources

Cost Type resources are a method of entering costs that are not calculated as a using a rate * work formula. They can be capital or operation expenditures such as shipping or travel. They are more flexible than fixed costs as you can add multiple cost type resources to the same activity. http://www....
by Intaver Support
Tue Dec 11, 2018 2:08 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Default constraint type
Replies: 1
Views: 1898

Re: Default constraint type

In RiskyProject you cannot set a default setting for the constraint typ. In RiskyProject, when you add a new task the constraint type will always default to As Soon as Possible. The reason for this is that in schedule risk analysis hard constraints of any kind should be used as this will prevent the...
by Intaver Support
Sun Nov 18, 2018 12:54 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Defining Uncertainty for Lags
Replies: 1
Views: 1951

Re: Defining Uncertainty for Lags

The Predecessor tab, which is located in the Task Information dialog box, is the central view for defining task predecessors. As well as defining predecessor link (Task ID, Name, and Type) you can also define the lag between the predecessor and successor as a 3pt uncertainty. To add the uncertainty ...
by Intaver Support
Sun Nov 18, 2018 12:47 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Irreducible Risk
Replies: 1
Views: 1898

Re: Irreducible Risk

Irreducible risk is sum of the aleatory risk, which is modeled using 3 point estimates for Low, Most Likely, and High for duration and cost, and residual risk that remain due to risk events or epistemic risks that cannot be completely eliminated. Often irreducible and residual risk are considered eq...
by Intaver Support
Sun Nov 18, 2018 12:43 pm
Forum: Project Portfolio Risk Management
Topic: Increasing performance for simulations on large schedules
Replies: 1
Views: 2300

Re: Increasing performance for simulations on large schedules

With extremely large projects (>50,000) running simulations can be an arduous task. Just loading data into applications can take hours and is one of the reasons that it is not a recommended practice. However, some mega projects require this analysis as part of their Integrated Program Management (IP...
by Intaver Support
Sun Nov 04, 2018 11:37 am
Forum: Project Portfolio Risk Management
Topic: Exporting XML to MS Project
Replies: 1
Views: 1935

Re: Exporting XML to MS Project

This depends on the objectives for running the analysis? There are a few issues with exporting the results back to MSP that you need to consider: 1. When you open the xml file, if you try import into an existing file, it could overwrite data not directly associated with the simulation results such a...
by Intaver Support
Sun Nov 04, 2018 11:35 am
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Using percentiles to calculate management baselines
Replies: 1
Views: 2064

Re: Using percentiles to calculate management baselines

If you want to use the results of the simulation to create a risk adjusted baseline that the percentile that you use is really a judgement call. Typically, customers who do use the feature export out the Base results (the average durations for each task) to xml which can then be imported into schedu...