Search found 879 matches

by Intaver Support
Wed Apr 22, 2020 5:06 pm
Forum: Project Portfolio Risk Management
Topic: Number of Projects in RiskyProject Enterprise
Replies: 2
Views: 4763

Re: Number of Projects in RiskyProject Enterprise

If you use SQL Server express there is a limit of total database size. SQL Server Express does not support databases larger than 10 GB. It means that you may experience limits on documents attached to risks, as well as very large schedules.
by Intaver Support
Wed Apr 22, 2020 5:02 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Exporting RiskyProject results to Primavera P6
Replies: 1
Views: 1098

Re: Exporting RiskyProject results to Primavera P6

There are a number of way to do it: 1. Use Microsoft Project XML export format. Go to File -> Export -> XML. Save results to the file and import it to Primavera P6. You can export deterministic project schedule or result of risk analysis associated with certain percentile. 2. Use Excel Export then I...
by Intaver Support
Wed Apr 22, 2020 4:47 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Unique Task IDs After Import from Primavera P6
Replies: 1
Views: 1059

Re: Unique Task IDs After Import from Primavera P6

Unique Task IDs should be including with the file using the "Unique Task ID" field. Here is a snip from an XER file.: MS Project also has UIDs. We have used them extensively when rendering Master Projects. To view unique task: 1. In any Task view, such as schedule, right click on the column. 2. Sele...
by Intaver Support
Tue Mar 31, 2020 5:39 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Modeling Probabilistic Activities in MS Project or RiskyProject
Replies: 1
Views: 1361

Re: Modeling Probabilistic Activities in MS Project or RiskyProject

If you would like to maintain the branching structure in MS Project. We recommend using the Active/Inactive Task feature. To inactivate a task(s): Once you have created your schedule in MS Project, select the branch that you do not want to be on the critical path. On the Tasks tab, click Inactivate....
by Intaver Support
Tue Mar 31, 2020 5:29 pm
Forum: Project Portfolio Risk Management
Topic: Using Branching to Model Response Plans
Replies: 1
Views: 899

Re: Using Branching to Model Response Plans

The response plan is meant to be a high level model of a response to a risk with schedule and cost impacts, but it doesn’t add any activities, just the cost and schedule impact that those additional activities would have. In this way, response plans are very much like risk outcomes, but allow do doc...
by Intaver Support
Sun Mar 15, 2020 9:45 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Task Resource Allocation Units
Replies: 1
Views: 2733

Re: Task Resource Allocation Units

In resource allocation, there are two different settings that you must take into account, the maximum units and the assignment units. • Maximum units: Specifies how much time a work resource has available for work on all tasks in a project and is used to calculate how much time a work resource can s...
by Intaver Support
Sun Mar 15, 2020 9:43 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Resource Overallocation Chart
Replies: 1
Views: 2911

Re: Resource Overallocation Chart

The resource allocation chart presents resource allocation information over period covered by the project. You can select four different types of resource charts. Right-click on the chart and select a chart type from the shortcut menu. http://www.intaver.com/images/RR_Forum_Alloc.png • Peak units : ...
by Intaver Support
Sun Mar 15, 2020 9:39 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Resource Leveling
Replies: 1
Views: 2870

Re: Resource Leveling

RiskyProject does not support resource leveling. Probabilistic resource leveling would most likely not provide a valid result and in most cases would be technically unfeasible due computer performance and differing leveling algorithms that are used by different scheduling software. This refers to ho...
by Intaver Support
Sat Feb 22, 2020 5:51 pm
Forum: Project Portfolio Risk Management
Topic: Saving Results to Baselines
Replies: 1
Views: 5269

Re: Saving Results to Baselines

With all previous versions prior to the release of version 7.1, probabilistic results were not saved with baselines. All risk and uncertainties could be saved, but you can only view the deterministic results in the Manage Baseline views. Previous version is shown below. http://www.intaver.com/images...
by Intaver Support
Sat Feb 22, 2020 5:44 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Generating Risk Adjusted Margins
Replies: 1
Views: 4495

Re: Generating Risk Adjusted Margins

1. Set the High Results the simulations to p80 in the Project Options > Calculation tab. http://www.intaver.com/images/RP_Forum_Margin1.png 2. Run the simulation. 3. In the Reports > Simulation Results view, hide all of the columns with the exception of the Task Name, Base Duration (Duration Base – ...
by Intaver Support
Sat Feb 22, 2020 5:34 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Export Results of Analysis
Replies: 1
Views: 4216

Re: Export Results of Analysis

With RiskyProject version 7, we recommend using the Export to Excel feature. 1. In Reports tab, set up the Simulation Results report to include the results you want to export to Excel. http://www.intaver.com/images/RP_Forum_ExcelExport1.png 2. From the File menu, click Export > Microsoft Excel http:...
by Intaver Support
Fri Jan 31, 2020 7:33 pm
Forum: Project Portfolio Risk Management
Topic: Updates in MSP file are not reflected in RiskyProject
Replies: 1
Views: 3984

Re: Updates in MSP file are not reflected in RiskyProject

if you are switching back and forth from MSP to RiskyProject you should use the button that appears in RiskyProject when you use the Addin.

Image
by Intaver Support
Fri Jan 31, 2020 7:31 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Conditional Branching not working?
Replies: 1
Views: 4938

Re: Conditional Branching not working?

There is known issue with the Finish Time conditions in version 7. This issue has been fixed in our latest update 7.1.
Below is a screenshot showing how conditional branching using finish times is currently implemented.

Image
by Intaver Support
Fri Jan 31, 2020 7:26 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Creating post mitigated schedules
Replies: 1
Views: 3775

Re: Creating post mitigated schedules

Mitigation plan are part of the qualitative risk management, but they do not impact the current schedule when you run a Monte Carlo simulation because the plan is not associated with any specific activities or costs in the schedule. To create a post mitigated schedule based upon the results of a sim...
by Intaver Support
Thu Jan 02, 2020 10:58 am
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Scenario Analysis
Replies: 1
Views: 4749

Re: Scenario Analysis

To analyze multiple scenarios, you must create multiple baselines (scenarios) and save them with their results. Cumulative probability for multiple baselines can be plotted on the same chart. First you need to create at least 2 baselines and save the results with the baseline: for example, pre and p...