Joint confidence level chart
I think the tooltip in Joint Confidence Level chart is incorrect. Duration is 8 times smaller than it supposes to be, however chart itself is correct and all samples are displayed properly.
- Mon Jan 18, 2016 11:12 am
- Forum: Project Portfolio Risk Management
- Topic: Permission to delete risks
- Replies: 1
- Views: 9252
Permission to delete risks
We use RiskyProject Enterprise. We need to ensure that we give permission to delete risks only to experienced managers, not to all users. How to do it?
- Tue Nov 03, 2015 4:15 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Risk Chart question
- Replies: 1
- Views: 9562
Risk Chart question
One of our divisions started using RiskyProject and it seems to provide all the standard monte carlo analysis reports. You also have a risk chart view, it looks interesting but we are not quite sure how we can use it to communicate the results to management.
- Sun Oct 25, 2015 12:29 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Filtering risks that are shown in risk register
- Replies: 1
- Views: 10480
Filtering risks that are shown in risk register
We would like to be able to show specific risks based upon location or project phase with priority based on risk score from monte carlo risk analysis, is there any way to do this?
- Sun Oct 25, 2015 12:28 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Can you risk resource costs
- Replies: 1
- Views: 10597
Can you risk resource costs
In the Assign to Tasks or Resources view in the Risk Register, we have added a risks to a resource. One is a schedule risk, but the other involves the cost of the risk. We assigned a fixed cost risk, but do not see any impact from after performing the monte carlo risk analysis. Are we doing somethin...
- Wed Sep 16, 2015 4:03 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Risks Assigned to the Project Schedule
- Replies: 1
- Views: 8960
Risks Assigned to the Project Schedule
Is there an easy way to quickly view how all project risks are assigned? As part of our project reviews we someway to show and justify our risk assignment.
- Wed Feb 07, 2007 4:06 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Risk wizard
- Replies: 1
- Views: 19752
Risk wizard
I would suggest employing "risk wizard" to define risks in RiskyProject. "Risk wizard" can be very good tool to capture information about risks probabilities, moment of risks, etc. You can apply for example "probability wheel" to come up with probabilities. Overall I like your software very much. I ...
- Wed Feb 07, 2007 4:02 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Risk project limitations
- Replies: 1
- Views: 17002
Risk project limitations
I'm trying to import schedule from Primavera to RiskyProject. The project has around 10000 activities. Can I do so?