Search found 20 matches
- Tue May 04, 2021 9:03 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Configuring Risk Matrix for Quantitative Risk Analysis
- Replies: 1
- Views: 13286
Configuring Risk Matrix for Quantitative Risk Analysis
I am confused by the idea that the risk impact 'Duration' has a percentage value in the 'Format Risk Matrix'. In my experience the only 'probability classes' are expressed in percentages, the duration classes in time (i.e. days) and the cost impact in money. It is only when I use the 'Drag 'n Drop R...
- Tue Apr 17, 2018 9:55 am
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Automatic Upgrades
- Replies: 1
- Views: 12747
Automatic Upgrades
Does RiskyProject include any automatic update software feature?
- Sun Jan 07, 2018 12:05 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Fixed delay from 2 to 10 days
- Replies: 1
- Views: 18195
Fixed delay from 2 to 10 days
Is any way to define risk outcome within certain margins? For example, I have a task than can be delayed in case of certain risk 2 – 10 days. I don’t know exactly on how much
- Sun Jan 07, 2018 11:59 am
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Work histogram
- Replies: 1
- Views: 12712
Work histogram
I have three work resources assigned to work. Performed Monte Carlo simulations. I now want to see on statistical distribution of work of each resource. How to do it?
- Mon Jan 18, 2016 10:53 am
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: How to define distribution using historical data
- Replies: 1
- Views: 11930
How to define distribution using historical data
Have have a number samples with historical duration of some tasks. How can we use it to define statistical distribution for task duration?
- Wed Dec 23, 2015 2:01 pm
- Forum: Project Portfolio Risk Management
- Topic: Project risk score scale
- Replies: 1
- Views: 10214
Project risk score scale
I saw a risk scale on the project summary diagram. What does it mean and how it is calculated?
- Wed Dec 23, 2015 11:30 am
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Probabilities outside of the distributions cut off
- Replies: 1
- Views: 13242
Probabilities outside of the distributions cut off
Looks like the distribution in RiskyProject only considers the duration from Low to High (there is a kind of 'cut' at the beginning/end). Is that right? Because sometimes projects/tasks have so much delay that they will take longer than the highest duration.
- Mon Nov 09, 2015 10:32 am
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Restoring Links with Microsoft Project files
- Replies: 1
- Views: 9951
Restoring Links with Microsoft Project files
I have made a *.mpp project and from the MS project started the riskyproject application. However when I move both files I am not able maintain the link between the two program. What shall I do? Where can tie files together again?
- Thu Sep 10, 2015 10:23 am
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Showing % complete on Gantt Chart
- Replies: 1
- Views: 10203
Showing % complete on Gantt Chart
In Microsoft Project you can show actuals on the Gantt Chart. Actuals are shown in a different color on the bar. It is a quick visual way to see approximately how much progress there has been on each task. Is there any way to do this in RiskyProject?
- Thu Sep 10, 2015 10:22 am
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Frequency Histogram for Monte Carlo Simulations
- Replies: 1
- Views: 11596
Frequency Histogram for Monte Carlo Simulations
When we do the Monte Carlo simulations we prefer to use the histograms as our key chart rather then just data tables. My chart right now has about 20 bars, I would like to bring this down to about 10 -12.
- Mon Dec 17, 2012 10:19 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Do I need to populate the register?
- Replies: 3
- Views: 17342
Re: Do I need to populate the register?
Where default risk probability and outcome is comming from? I would like to set default probability equal 20% not 15%.
- Wed Aug 29, 2012 4:38 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Event Chain Diagram
- Replies: 10
- Views: 38987
Re: Event Chain Diagram
I like arrows of different colors which represent risks in Gantt Chart. What I discovered that if task has very many risks assigned not all arrows are displayed. Is it correct? How many arrows can be displayed on the task bar?
- Wed Aug 29, 2012 4:33 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Scatter Plot in RiskyProject
- Replies: 5
- Views: 20476
Scatter Plot in RiskyProject
Does RiskyProject generate a scatter plot, for example project duration vs. task duration or project finish time vs. task finish time?
Thanks,
Hato
Thanks,
Hato
- Thu Apr 26, 2012 11:26 am
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Do I need to populate the register?
- Replies: 3
- Views: 17342
Do I need to populate the register?
Questions:
1. Is it necessary to populate the Risk Register before doing a quantitative analysis?
2.How do I view/print histograms of the quantitative analysis results? (I\'m using RiskyProject Lite)
1. Is it necessary to populate the Risk Register before doing a quantitative analysis?
2.How do I view/print histograms of the quantitative analysis results? (I\'m using RiskyProject Lite)
- Sat Aug 27, 2011 8:58 am
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: RiskyProject and Critical Chain
- Replies: 1
- Views: 12789
RiskyProject and Critical Chain
Hello,
We are in a process of implementation Critical Chain project management process. Can we use RiskyProject for Critical Chain?
We are in a process of implementation Critical Chain project management process. Can we use RiskyProject for Critical Chain?