Search found 20 matches

by Hato
Tue May 04, 2021 9:03 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Configuring Risk Matrix for Quantitative Risk Analysis
Replies: 1
Views: 12570

Configuring Risk Matrix for Quantitative Risk Analysis

I am confused by the idea that the risk impact 'Duration' has a percentage value in the 'Format Risk Matrix'. In my experience the only 'probability classes' are expressed in percentages, the duration classes in time (i.e. days) and the cost impact in money. It is only when I use the 'Drag 'n Drop R...
by Hato
Tue Apr 17, 2018 9:55 am
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Automatic Upgrades
Replies: 1
Views: 12210

Automatic Upgrades

Does RiskyProject include any automatic update software feature?
by Hato
Sun Jan 07, 2018 12:05 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Fixed delay from 2 to 10 days
Replies: 1
Views: 17301

Fixed delay from 2 to 10 days

Is any way to define risk outcome within certain margins? For example, I have a task than can be delayed in case of certain risk 2 – 10 days. I don’t know exactly on how much
by Hato
Sun Jan 07, 2018 11:59 am
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Work histogram
Replies: 1
Views: 12276

Work histogram

I have three work resources assigned to work. Performed Monte Carlo simulations. I now want to see on statistical distribution of work of each resource. How to do it?
by Hato
Mon Jan 18, 2016 10:53 am
Forum: RiskyProject: Project risk management and risk analysis software
Topic: How to define distribution using historical data
Replies: 1
Views: 11801

How to define distribution using historical data

Have have a number samples with historical duration of some tasks. How can we use it to define statistical distribution for task duration?
by Hato
Wed Dec 23, 2015 2:01 pm
Forum: Project Portfolio Risk Management
Topic: Project risk score scale
Replies: 1
Views: 10007

Project risk score scale

I saw a risk scale on the project summary diagram. What does it mean and how it is calculated?
by Hato
Wed Dec 23, 2015 11:30 am
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Probabilities outside of the distributions cut off
Replies: 1
Views: 13106

Probabilities outside of the distributions cut off

Looks like the distribution in RiskyProject only considers the duration from Low to High (there is a kind of 'cut' at the beginning/end). Is that right? Because sometimes projects/tasks have so much delay that they will take longer than the highest duration.
by Hato
Mon Nov 09, 2015 10:32 am
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Restoring Links with Microsoft Project files
Replies: 1
Views: 9817

Restoring Links with Microsoft Project files

I have made a *.mpp project and from the MS project started the riskyproject application. However when I move both files I am not able maintain the link between the two program. What shall I do? Where can tie files together again?
by Hato
Thu Sep 10, 2015 10:23 am
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Showing % complete on Gantt Chart
Replies: 1
Views: 10006

Showing % complete on Gantt Chart

In Microsoft Project you can show actuals on the Gantt Chart. Actuals are shown in a different color on the bar. It is a quick visual way to see approximately how much progress there has been on each task. Is there any way to do this in RiskyProject?
by Hato
Thu Sep 10, 2015 10:22 am
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Frequency Histogram for Monte Carlo Simulations
Replies: 1
Views: 11445

Frequency Histogram for Monte Carlo Simulations

When we do the Monte Carlo simulations we prefer to use the histograms as our key chart rather then just data tables. My chart right now has about 20 bars, I would like to bring this down to about 10 -12.
by Hato
Mon Dec 17, 2012 10:19 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Do I need to populate the register?
Replies: 3
Views: 17147

Re: Do I need to populate the register?

Where default risk probability and outcome is comming from? I would like to set default probability equal 20% not 15%.
by Hato
Wed Aug 29, 2012 4:38 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Event Chain Diagram
Replies: 10
Views: 38639

Re: Event Chain Diagram

I like arrows of different colors which represent risks in Gantt Chart. What I discovered that if task has very many risks assigned not all arrows are displayed. Is it correct? How many arrows can be displayed on the task bar?
by Hato
Wed Aug 29, 2012 4:33 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Scatter Plot in RiskyProject
Replies: 5
Views: 20255

Scatter Plot in RiskyProject

Does RiskyProject generate a scatter plot, for example project duration vs. task duration or project finish time vs. task finish time?

Thanks,
Hato
by Hato
Thu Apr 26, 2012 11:26 am
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Do I need to populate the register?
Replies: 3
Views: 17147

Do I need to populate the register?

Questions:
1. Is it necessary to populate the Risk Register before doing a quantitative analysis?

2.How do I view/print histograms of the quantitative analysis results? (I\'m using RiskyProject Lite)
by Hato
Sat Aug 27, 2011 8:58 am
Forum: RiskyProject: Project risk management and risk analysis software
Topic: RiskyProject and Critical Chain
Replies: 1
Views: 12664

RiskyProject and Critical Chain

Hello,
We are in a process of implementation Critical Chain project management process. Can we use RiskyProject for Critical Chain?