Configuring Diagnostic Tests
RiskyProject can perform up to 21 tests on a project schedule. By default, all of them are enabled. You can enable of disable tests, define their
severity, as well as define other parameters associated with tests.
To configure schedule diagnostics:
- Click the Schedule tab.
- Select Schedule Diagnostics.
- Click on Configure Diagnostic Tests.
- Enable or disable tests you want to run.
- Select color indicating relative severity level of each test.
- Select number of days for 2 tests: “Task duration is greater than …” and “Task has float greater than …”
- Click OK.