Quantitative Analysis of Non-Schedule Risks
If you have risks that are assigned to non-schedule categories, such as safety, security, environment, etc. you can generate statistical
distributions of these risks in Project Summary View.
Here is how probability and impact of non-schedule risk are calculated:
- Risks could affect different non-schedule categories with certain probability and impact.
- Risk 1: probability = 30%, impact = 60% for category technology. It means that this risk will increase technological problems by 60%.
- Risk 2 probability = 40%, impact = 35%.
- Total probability depends on how these risk events are correlated with each other. If they are 100% correlated probability will be 40%.
- Total impact will be sum of impact on individual risks: 95%.
- Monte Carlo simulations are performed.
- Impact of all risks for each risk category will be summed.
- Results are shown in the Project Summary View.
Statistical Distribution for non-schedule risk will be shown in Project Summary View
Non-schedule risks may have probabilistic risk outcome. For example, impact on safety may be between 10% and 20%.
It will be reflected in statistical distribution for Safety.