Search Help:



About Portfolio Options

In RiskyProject Enterprise Portfolio options are very similar to Project options in RiskyProject desktop. Portfolio Options are applied to all new projects in the database and require administrative permissions to configure. To access in RiskyProject Enterprise Portfolio Options go to File > Options. Portfolio Options dialog has the same tabs as Project Options in RiskyProject desktop, except it has General tab instead of View tab. General tab includes How Portfolio options are applied setting in addition to other view settings.

These are two ways by which portfolio options are applied to a particular project:

  • Apply portfolio options to all new or imported projects - the user may change individual project options at any time.
  • Use only portfolio options - inividual project options cannot be changed.

To change these rules:

  1. Click the Projects tab.
  2. In the Portfolio Settings group, click Portfolio Options.
  3. Click the General tab.
  4. Select on the rules to apply to the Portfolio.
  5. Click OK.

Individual Risk Matrixes for Different Projects or Users

By default, there is one global risk matrix for all users or projects. However, you have the option to assign individual risk matrixes for different projects or users. If you assign individual risk matrixes for a particular summary project, these will automatically be propagated to all subprojects. If you assign individual matrixes to the users, these will be assigned to all users within a selected user group in your organizational breakdown structure.

To define individual matrixes for users and projects:

  1. Click the Risks tab and then click on Format Risk Matrix
  2. Click on Advanced Settings
  3. Select Risk Matrix Settings: global, per project or per user

See also

Setting up Your Project Defaults
About Risk Visibility (Approval) Rules

Legal Notice Privacy Statement Copyright © Intaver Institute Inc., 2002-. All Rights Reserved.