Schedule Diagnostics Based on DCMA 14 Point Assessment
DCMA Point Assessments includes the following tests
DCMA 14 point Schedule Assessment is performed automatically when you click on Schedule Diagnostics. For some tests, additional settings are required:
- For DCMA-6, DCMA-7, DCMA-12, you may need to enable critical path calculation: in File > Options, go to Calculation tab and select Calculate Critical Path.
- For DCMA-9, you may need to define project status date. File > Options > Calendar tab.
- DCMA-12 can run slow on large schedules. It is possible to enable/disable DCMA-12 test using a checkbox in Welcome to Schedule Diagnostics dialog.
- For DCMA-13, right-click on row ID and click on Milestone for DCMA 13-CPLI and then select milestone which is required for this test.
- You can double-click on each DCMA test and view detailed information about particular metric as part of RiskyProject Help System.
To view Help you must be connected to Internet.
- You can copy test results to clipboard: right-click on row ID and click on Copy.
- You can see issues associated with DCMA tests within list of issues (top list box) by clicking on the particular DCMA test.
See also:
About Schedule Diagnostics