Search Help:



Modifying Projects

To modify a project schedule, you must open it. If the project has risks and uncertainties, they will be reflected in the project portfolio as soon the project is saved. In particular, risk scores will be re-calculated and the Project Gantt chart will be updated. Project names and project priorities can be updated without opening the project. You may be required to modify the project start time.

To modify a project start time:

  1. Open the project.
  2. Click the Schedule tab, and in the Settings and Options group, click Project Settings.
  3. Click on the Project Start Time box. A calendar opens.
  4. Select the new project start time from the calendar.
  5. Click OK. Close the project and the new start time will be reflected in the project hierarchy.

See also

Creating a Portfolio Hierarchy

Legal Notice Privacy Statement Copyright © Intaver Institute Inc., 2002-. All Rights Reserved.