Viewing results for resource assignments

You may view the statistical distribution of work associated with each resource. Statistical distributions are only shown for resources that are designated work rather than material.

  1. Double-click a task ID to open the Task Information dialog box
  2. Click the Resources tab.
  3. Right-click on a resource assignment ID.
  4. Choose Simulation Results... to view the work associated with selected resource assignment.

RiskyProject allows you to quickly view the cost (revenue, if income in any task is defined), duration, start time and finish times uncertainties associated with each task.