Viewing the project summary frequency charts
The frequency charts are interactive and show the risk profile for
each project parameter: Cost, Finish Time, and Duration.
- Drag the slider across a chart to view the chance that the
project parameter will equal a certain value.
- Double-click on a chart to enlarge it. The enlarged chart
provides several different features including:
- Cumulative probability chart
- Full access to all statistical data for the selected
parameter
- Click on the Statistical Data for Work
button to view the distribution for work. Work data is correlated to
project duration distributions.
- Right-click on the chart to view a full menu of analysis and
copying options.
-
The low and high results of probabilistic calculations (cost,
duration, and finish times) are associated with P1/P99, P5/P95,
P10/P90, or any custom percentiles. These are defined in the Options
(Calculation tab).
-
You may customize frequency charts either using Format -> Format
Frequency Chart or by right clicking of frequency chart and
selecting Options.
See also
Task Simulation Results
Task Simulation Results Options |