Viewing the project summary frequency charts

The frequency charts are interactive and show the risk profile for each project parameter: Cost, Finish Time, and Duration.

  1. Drag the slider across a chart to view the chance that the project parameter will equal a certain value.
  2. Double-click on a chart to enlarge it. The enlarged chart provides several different features including:
    • Cumulative probability chart
    • Full access to all statistical data for the selected parameter
  3. Click on the Statistical Data for Work button to view the distribution for work. Work data is correlated to project duration distributions.
  4. Right-click on the chart to view a full menu of analysis and copying options.

  • The low and high results of probabilistic calculations (cost, duration, and finish times) are associated with P1/P99, P5/P95, P10/P90, or any custom percentiles. These are defined in the Options (Calculation tab).
  • You may customize frequency charts either using Format -> Format Frequency Chart or by right clicking of frequency chart and selecting Options.