| Setting up 
			risk defaults
          You 
			define defaults for Global and Local risks in the Risks tab. These 
			parameters are used when you create a new risk.
                    Click the Schedule tab. In the Settings group, 
                    click Options..   Click the Risk tab.  Enter the default settings for the chance of:
                      
                            risk occurrencetype of outcomeresult of outcome. 
                                The result of outcomes is used to calculate outcomes for 
			                    Relative Delay and Cost or Income Increase, as well as all user 
			                    defined risk outcomes for non-schedule risks.
Select the default distribution for the moment of risk. This 
			distribution is used to define when risk would occur during the 
			course of project. It is defined by distribution type (uniform or 
			triangular), and three parameters defining start, most likely, and 
			finish time of risk occurrence expressed as a percent of total task 
			duration starting from the beginning of the task. For example:
            
                 Distribution: TriangularStart: 50%Most likely: 80%End: 100%With this example with a task of 10 days, the risk could occure after tje 5th day 
                    and would most likely would occur on 8th 
			day. Select the risk chance option. The chance can be defined per task 
			(by default) or per duration unit. For example, 30% chance that task 
			can be restarted per day. If task duration is 2 days, chance of risk 
			occurrence per task will be 60%. This option works for all projects. 
			You cannot have different risks with chance applied to the duration 
			unit or chance applied to the complete task for the same project at 
			the same time.
                Enable or disable automatic generation of Risk ID and define rules for 
                    automatic generation of risk ID. 
                Enable or disable statistical distribution for risk outcomes. For more 
                    information about statistical distribution of risk outcomes, read Uncertainties 
                    in Risk Outcomes or click What is it?
                Define correlation of risk assignment. One risk can be assigned to different tasks or resources or the risk can be assigned globally
				(to all tasks or resources). These risk events may occur at the same time (risk assignments are correlated) on in different times 
				(risk assignments are not correlated). If check box Risk assignments to different tasks are correlated is checked, all local and 
				global assignments of the same risk will be correlated by default. You can always change correlation of local risk assignment:
				
					For more information click on What is it? button. This feature is available for version 6.1 and laterGo to the Risk Assignment view or Task Information/Resource Information dialog boxes.Double click on risk assignment IDGo to correlation tabSet up risk visibility (approval) rules (RiskyProject Enterprise only). For more 
                    information read Risk visibility (Approval) rules for RiskyProject Enterprise.
                 
      See alsoRisks in RiskyProjectRisk visibility (Approval) rules for RiskyProject Enterprise
 Setting up your projects
 |