Results Gantt Chart View
           
			RiskyProject displays the start and finish ranges of each task in 
			the Result Gantt view. The calculated project and baseline schedules 
			are shown in the same Gantt chart. You can use the task bar for 
			deterministic current schedule to compare deterministic and 
			probabilistic schedules. 
            
                - Task Name: Name of the task. 
 
                - Success Rate: The chance that a task will be completed. A task can be cancelled in one 
                    of four cases:
                - if the risk cancels task or cancel tasks + all successor has 
                    occurred
 
				- if task has reached a deadline
 
				- if project has reached a deadline 
                    and task finish time is beyond such deadlines.
                
 - success rate can be calculated in 
                    of probabilistic calculation. It equals number of iterations in which the task has been 
                    completed divided by the total number of iterations. 
  
					
                 - Base Duration: Enter in the base estimate for the task duration 
 
                - Low Duration: Enter in the low estimate for the task duration 
 
                - High Duration: Enter in the high estimate for the task duration 
 
                - Low Duration (Mean): Low duration as a result of probabilistic calculations. It 
                    is blank for current schedule calculations. Can be minimum, P1, P5, P10. It is 
                    defined in Options (Calculation tab). 
 
                - Mean Duration: Duration as a result of probabilistic calculations: difference 
                    between task's mean finish time and mean start time. It is blank for current 
                    schedule calculation. Please note, that "Duration Mean - result" and "Duration 
                    Mean - statistical result" can be different 
 
                - High Duration(Mean): High duration as a result of probabilistic calculations. It 
                    is blank for current schedule calculation. Can be maximum, P90, P95, P99. It is 
                    defined in Options (Calculation tab). 
 
                - Start Mean: Mean start time as a result of probabilistic calculations. 
 
                - Finish Mean: Low finish time as a result of probabilistic calculations. 
                    Will have no value in the current schedule calculation. Can be minimum, P1, P5, 
                    P10. It is defined in Options (Calculation tab). 
 
                - Distrib, Dur: You can select the statistical distribution for the duration to be 
                    used in the probabilistic calculations. Distribution can be Undefined, Normal, 
                    Lognormal, Uniform, and Triangular. Undefined distribution means that Low 
                    Duration and High Duration is ignored, and duration is Base in all iterations. 
                    If low, base, and high default durations are the same, distribution is set to 
                    Undefined. In other cases, default distribution is Triangular. For more 
                    information, see "How to define distribution for Start Time, Cost, Income, and 
                    Duration". 
 
                - Seed, Dur. Seed is a starting parameter for random number generation and is used 
                    to calculate duration. If you have two tasks, and they have strong positive 
                    correlations between their durations, you can make their seeds the same. For 
                    example: low duration of one task will coincide with low duration of another 
                    task. Seeds do not affect deterministic (current schedule) calculation. 
 
             
            
			 
			 
           
			You can display Result Gantt associated only with low (optimistic) 
			and high (pessimistic) results. 
			 
			Showing or Hiding Low/High Results
			 
                 - Right-click on the chart and a shortcut menu opens.
 
                 - From the shortcut menu, choose one of the following viewing 
			options:
				
					- Show Both Low/High Results
 
					- Show Low Results
 
					- Show High Results
 
					- Show Current Schedule.
 
				 	
			  
            
                See also
				About Project Tasks 
				Gantt View 				
  |