Importing data from other project management software and keeping risk assignment

Sometimes you may want to import project schedule from Microsoft Project or other software and keep existing risk assignment. It can be useful when you imported project schedule from Microsoft Project or other software, assigned risks in RiskyProject, and then updated project schedule in Microsoft Project.

1. On the File menu, click Import.

2. Select whether or not you want to import the risks already assigned to the project. RiskyProject will associate assigned risks with new tasks based on unique task IDs. However if you rename a task in Microsoft Project, this will remove all risk links to the renamed task.

See also

Importing Project Schedules