Adding 3-point estimates
Adding 3-point estimates for task
duration and start times
-
On the Gantt view, double-click on the task ID.
-
Click the General tab.
-
Select a Base, Low, and
High dates for Start Time.
-
Select a Base, Low, and
High values for Duration. By default when
you enter a value for duration, the default values for Low and High
are calculated based on the defaults set in the Duration
Options.
-
Click OK to save the estimates.
Adding 3-point estimates for task cost
and income
-
On the Cost and Revenue
view, select the task to which you want to add cost and income
estimates
-
Enter cost data for Cost Low,
Cost, and Cost High. By default
when you enter a value for Cost, the default values for Low and High
are calculated based on the Cost defaults set in the Cost
Options.
-
Enter income data for Inc. Low, Income,
and Inc. High.
-
Click OK to save the estimates.
Adding 3-point estimates for lags
-
On the Gantt view, double-click on the task ID.
-
Click the Predecessor tab.
-
Enter Low, Base, and
High Lag. Default statistical distribution will be
generated automatically. There are only two distributions for lag:
Uniform and Triangular.
-
Click OK to save the estimates.
See also
Adding 3-point estimates
Distribution Fitting using Stat--Fit
|