About Uncertainties in Risk Outcomes

You may define risk outcome as a range defined by statistical distribution:

After you enter probabilistic risk outcomes and click OK, RiskyProject will perform Monte Carlo simulation and calculate risk impact based on the mean of the statistical results.

Enable probabilistic risk outcomes:

  1. On the ribbon, click the Schedule tab and then Options.
  2. Click the Risk tab.
  3. Select the Enable statistical distribution for risk outcome checkbox.

Once enabled, this setting will be the default setting for all RiskyProject files on your computer.

See also

About Risk Attributes