Project View
The Baseline Gantt view is where you create and view the baseline
project schedule.
Default fields
- Task ID: Double-click to open the Task
Information dialog box.
- Base Duration:
Enter in the base estimate for the
task duration
- Low Duration:
Enter in the low estimate for the
task duration
- High Duration: Enter in the high estimate for the
task duration
-
Base Start Time: is used to calculate current project schedule.
It also used to calculate start time of each iteration of the probabilistic
calculation. Note that in most cases, the Start Time is calculated automatically
based on the predecessor finish time and lag. If a task does not have
predecessors, the default start time is the current time or default start time
set in Options. If you update the Start
Time, the Constraint is set to Must
Start On.
- Finish Time: Base Finish Time is used to calculate current
project schedule. Note that in most cases, Finish Time is calculated
automatically based on Start Time and duration. If you update the Finish Time,
the Constraint is set to Must Finish On.
- Resource: Enter or select a resource to assign
it to the task.
- Predecessors: A list of predecessors for the current task.