Creating a baseline

Once you have run a simulation on your project, you can save the results as a baseline.

In this example, a user has just completed a simulation and is saving the Base results.

  1. Click the Schedule tab. In the Baselines group, click Set.
  2. Enter a name for the baseline. By default, it is assigned "Baseline #_"
  3. Select the type of results (Low, Base, High, specific percentile, or Current Schedule and Results of Analysis) that you want to use for your baseline. It can be used to view multiple cumulative probability plots on the same chart.
  4. Click OK.
  5. If you are using probabilistic results for the baseline, you are prompted to disable all risks and uncertainties from the schedule.
    • Choosing Yes will in effect create a deterministic baseline out of the results you selected.
    • Choosing No will mean that all risks and uncertainties will remain. If you calculate this baseline again, this may cause a double count of the risks and uncertainties.

See also

Analyzing Risk Mitigation Efforts with Multiple Baselines
Comparing pre and post-mitigation baselines
Converting a baseline to a current schedule
Creating a mitigation or risk response plans

Legal Notice Privacy Statement Copyright © Intaver Institute Inc., 2002-. All Rights Reserved.