Creating a baseline
Once you have run a simulation on your project, you can save the
results as a baseline.
In this example, a user has just completed a simulation and is saving the Base
results.
- Click the Schedule tab. In the Baselines
group, click Set.
- Enter a name for the baseline. By default, it is assigned
"Baseline #_"
- Select the type of results (Low, Base, High, specific percentile, or Current Schedule and Results of Analysis) that you want to use for your baseline.
- Click OK.
- If you are using probabilistic results for the baseline, you are
prompted to disable all risks and uncertainties from the schedule.
- Choosing Yes will in effect create a
deterministic baseline out of the results you selected.
- Choosing No will mean that all risks
and uncertainties will remain. If you calculate this baseline again,
this may cause a double count of the risks and
uncertainties.
See also
Analyzing Risk Mitigation Efforts with Multiple Baselines
Comparing pre and post-mitigation baselines
Converting a baseline to a current schedule
Creating a mitigation or risk response plans
|