Success Rate

The chance that a task or project will be completed. A task success rate of 56% means that there is a 56% chance that this task will be completed and 44% percent chance that it will be canceled. A task can be canceled when either it reaches a task or project deadline, or if a risk with a Cancel task, Cancel Task + all successors or Cancel Project outcome type occurs. A project can be canceled either when it reaches the project deadline or if a task risk with a Cancel Project outcome occurs. The task success rate is shown on the Success Rate view, but it can be requested within any view. The Project success rate is shown in the Project Information view.