| Description |
Editable text, a list of predecessors for the current task. Example: 1+3day, 1SF+4day. It means: that predecessors are task 1 Finish-Start relationship with lag 3days and task 2 (Start-Finish relationship) with lag 4 days. Start-Finish is displayed as SF, Start-Start is SS, Finish-Finish is FF. Finish-Start does
|