Search Help:

Tracking Results

The probabilistic calculations always encapsulate the tracking information if it has been entered for a task. RiskyProject shows results of the tracking calculations in several different ways depending upon the view you are using to examine it.

Entering tracking data

  1. Select the task to which you want to enter the tracking data.
  2. Open the Task Information dialog box.
  3. Click the Tracking tab. By default, the first row should contain the actual start time with zero percent done.
  4. Click the row below the previous entry.
  5. Enter the status date or select it from the calendar.
  6. Enter the percentage of the task completed by the specified date. All dates and percentages must be consistent. For example, you cannot have a record with 60% completed before a record with 40% completed. In addition, you cannot have historical data with the date Jan 5,2004 before the record with Dec 14,2003.
  7. Optionally enter remaining duration parameters: low, base, and high duration, and statistical distribution for remaining duration. If you don’t enter this information remaining duration on each iteration will be calculated using extrapolation of original duration.
  8. Define parameters of statistical distribution for remaining duration (see Defining statistical distribution for remaining duration for more information).
  9. Type in a comment to record actual details of work completed. You can now view the Tracking chart.


  • To view any tracking information, including the percentage completed for summary tasks and the project, you must calculate the project.
  • Remaining duration information is used only for probabilistic analysis.

See also

Tracking Performance
Task Information Tracking
Legal Notice Privacy Statement Copyright © Intaver Institute Inc., 2002-. All Rights Reserved.