Risks must be assigned to calculate their impact. If risk is not
assigned to any tasks or resources it will remain in risk register,
but probability, impact, and score will not be shown.
RiskyProject has two types of risks assignment:
- Global Risk Assignments:
Global risk assignment are those risk assignments, which have a
chance of affecting the project as a whole and are not limited to
specific tasks or resources. For example, political or weather risks
would be assigned as global.
- Local Assignment: Local risk assignments
are those risks that have a chance of affecting only specific tasks
or resources. A local risk assignment can affect more than one task
or resource. For example, risks affecting the delivery of specific
equipment for a certain phase of a project would be assigned local.
You can edit or view risk assignments in the following dialog boxes
and views:

- RiskyProject flags any mutually exclusive alternative
outcomes whose sum or probabilities are greater than 100% with pink
shading. In these cases, the calculation results may be incorrect.
- Use the Indent and Outdent arrows to group risks and create
a risk breakdown structure.