About Calculation Types
RiskyProject has two types of calculations:
- Deterministic - this is the
default calculation automatically performed when you modify a
project schedule. As this calculation occurs automatically, you do
not need to press the Calculation button. This calculation uses the
Base input parameters (duration, start time, lag) without
calculating the effect of risk or uncertainty.
- Probabilistic (Monte Carlo simulations) – Use
this to calculate the project schedule and costs with uncertainties
and risks.
Enabling or disabling automatic Monte Carlo simulations for small projects
- Click the Schedule tab. In the Settings and Options
group, click Options. The
Options dialog box opens.
- Click the Calculations tab.
- From the Default Calculation for Small Projects option box, select one of the
two options:
- Current Schedule Calculation only
- Probabilistic Calculation (Monte Carlo simulations)
- Click OK. RiskyProject automatically determines which project is small based
on your computer’s performance and the size of the project
Running probabilistic calculations
Click the Calculation button on the Schedule tab. You may cancel the probabilistic
calculation at any time; however, if number of simulations performed
is less than 20, no probabilistic results will be calculated.
See also
RiskyProject Calculation Options
Defining the number of simulations
|