Adding 3-point estimates
Adding 3-point estimates for task
duration and start times
- On the Gantt view, double-click on the task ID.
- Click the General tab.
- Select a Base, Low, and
High dates for Start Time.
- Select a Base, Low, and
High values for Duration. By default when
you enter a value for duration, the default values for Low and High
are calculated based on the defaults set in the Duration
Options.
- Click OK to save the estimates.
Adding 3-point estimates for task cost
and income
- On the Cost and Revenue
view, select the task to which you want to add cost and income
estimates.
- Enter cost data for Cost Low,
Cost, and Cost High. By default
when you enter a value for Cost, the default values for Low and High
are calculated based on the Cost defaults set in the Cost
Options.
- Enter income data for Inc. Low, Income,
and Inc. High.
- Click OK to save the estimates.
Adding 3-point estimates for lags
- On the Gantt view, double-click on the task ID.
- Click the Predecessor tab.
- Enter Low, Base, and
High Lag. Default statistical distribution will be
generated automatically. There are only two distributions for lag:
Uniform and Triangular.
- Click OK to save the estimates.
See also
Assigning Low and High Estimates for Duration and Cost for Group of Tasks
Defining task distributions
|