Tracking Results
The probabilistic calculations always encapsulate the tracking information if it has been entered for a task. RiskyProject presents results of the tracking calculations in several different ways depending upon the view you are using to examine it.
|
View
|
How
Tracking information is presented
|
|
Baseline
Gantt
|
No
tracking information on the baseline schedule
|
|
Results
Gantt
|
Tracking
data is represented as green, yellow, and red bars. These bars
represent percent completed. It can be turned on and off when
you right click on Gantt chart and select “Show Tracking
Bars”. You can also click on
Tracking button from the Standard menu.
|
|
Success
Rate
|
Gantt
chart is drawn based on baseline schedule
|
|
Crucial
task
|
Gantt
chart is drawn based on baseline schedule
|
|
Tracking
Gantt
|
The
Tracking Gantt behaves in the same manner as the Results Gantt,
In addition, the percentage completed will be shown on the right
of the bar
|
|