Project Risk Management and Decision Analysis 

Tracking Results

The probabilistic calculations always encapsulate the tracking information if it has been entered for a task. RiskyProject presents results of the tracking calculations in several different ways depending upon the view you are using to examine it.

  

View

How Tracking information is presented

Baseline Gantt

No tracking information on the baseline schedule

Results Gantt

Tracking data is represented as green, yellow, and red bars. These bars represent percent completed. It can be turned on and off when you right click on Gantt chart and select “Show Tracking Bars”. You can also click on  Tracking button from the Standard menu.

Success Rate  

Gantt chart is drawn based on baseline schedule

Crucial task

Gantt chart is drawn based on baseline schedule

Tracking Gantt  

The Tracking Gantt behaves in the same manner as the Results Gantt, In addition, the percentage completed will be shown on the right of the bar