View Task Simulation Results

There are two ways that you can view the simulation results for a single task.

To view the results for a single task:

1. Right click on a task ID in any view. A shortcut menu opens.
2. Choose Task Simulation Results from the shortcut menu. The Monte Carlo Simulation Results dialog box opens

OR

1. From any of the views with a Gantt chart, select the task.
2. Double-click on the task in a Gantt chart. The Monte Carlo Simulation Results dialog box opens. 

Task uncertainties for Cost, Duration, Start Time and Finish Time are shown in the charts. . The charts are similar to charts in the Project Summary view, but show the results for the selected task only. 


For more information about frequency and cumulative probability charts, see “Using the Simulation Results Chart”.