Project Risk Management and Decision Analysis 

Milestones

A task can be flagged as a milestone. If you turn on Milestone the task bar within a Gantt chart is displayed as:

Any task with zero duration is automatically displayed as a milestone in the Gantt chart; however, any task can be marked as a milestone. The milestone flag is for display only and does not affect the project calculations.

If a task has no duration entered, it is automatically displayed as a milestone and you do not have to complete the following steps. If you want to flag a task that has duration, complete the following steps.

To create a milestone:

1. Select the task that you want to flag as a milestone.
2. Open the Task Information dialog box. See the About Task Start Time, Finish Time, and Duration topic to read more about opening the Task Information dialog box. 
3. Click the General tab.
4. Select the This task is a milestone check box.
5. Click OK.