Success Rate
The success rate or chance the task will be successfully completed is shown on the Success Rate Gantt chart.
Each task will be presented by different colors, which represents a range of success rates.
A task can be canceled in one of three cases:
· if the outcome Cancel task or Cancel task + all successors occurs, this cancels the tasks plus all successors which have occurred;
· if a task reaches a deadline, and action associated with deadline is set to cancel task; and
· if a project has reached a deadline and task finish time is beyond the deadline.
|