Result Gantt Chart
RiskyProject displays the start and finish ranges of each task in the Result Gantt view. The calculated project and baseline schedules are shown in the same Gantt chart. You can use the baseline task bar to compare baseline and probabilistic schedules.
To Show Baseline and Low/High results:
1. Right-click on the chart. A shortcut menu opens.
2. Choose Show Low/High Results and/or Show Baseline from the shortcut menu.
|