Project Risk Management and Decision Analysis 

Inputting Local Risks Using Risk View

You can define local risks using the Global Risk View. 

To assign risk from local view to local tasks or resources:

1. Select the Global Risk View.
2. Define a new risk.
3. Double click on the Risk ID field. The Risk Information dialog box opens.
4. Select either the Assign to Tasks or Assign to Resources tab.
5. Select a task or resource from the list.
6. Enable or disable risk for the particular task or resources if necessary

Notes:

  • If you assign and enabled a risk to a task using the Global Risk View ensure that in Global Risk view is disabled. Otherwise, risk may occur twice as global and as local risks. 
  • You can update the risk properties for all of the tasks and resources to which this risks is assigned using the Update Risk Properties button. For example, you can update a risk in the Global Risks view. Then select the Assign to Tasks or Assign to Resources tab and click the Update Risk Properties button 