User's Guide to
RiskyProject Professional
Task Related Fields
Total Cost (Base)
Name of parameters (shown on the tool tip)
Type of the field
Static Text
Short name (shown in the header)
Tot Cost
Description
Cost associated with resources assigned to the particular task plus fixed task cost. Calculated duration baseline calculation.
Related Fields
Fixed Cost (Low)
Fixed Cost (Base)
Fixed Cost (High)
Resource Cost
Copyright © Intaver Institute Inc., 2002-2006. All Rights Reserved