User's Guide to  

RiskyProject Professional

Back to RiskyProject Professional
Project Risk Management and Decision Analysis 

Task Related Fields

Success Rate

Name of parameters (shown on the tool tip)

Success Rate

Type of the field

Static Text

Short name (shown in the header)

Success

Description

The chance that a task will be completed. A task can be canceled in one of 3 cases:

  • if the risk cancels task or cancel tasks + all successor has occurred

  • if task has reached a deadline

  • if project has reached a deadline and task finish time is beyond such deadline

Success rate can be calculated in of probabilistic calculation. It equals number of iterations, then task has been completed divided on total number of iterations.

Related Fields

N/A


 

www.intaver.com products      solutions      support      partners      technology      company

Copyright © Intaver Institute Inc., 2002-2006. All Rights Reserved