Task Related Fields

Finish Time of the task (Base)    

Name of parameters (shown on the tool tip)

Finish Time of the task (Base)  

Type of the field

Calendar Control

Short name (shown in the header)

Finish Mean

Description

Base Finish Time is used to calculate baseline project schedule. Note that in most cases, Finish Time is calculated automatically based on a task’s Start Time and duration. If you update the Finish Time, the Constraint is set to “Must Finish On”. See “Start, Finish Times, and Constraints” for more details.  

Related Fields

Finish Time Low 

Finish Time High 


 