Project Risk Management and Decision Analysis 

Task Related Fields

Duration Low - baseline

Name of parameters (shown on the tool tip)

Duration Low - baseline

Type of the field

Edit Box with Spin Control

Short name (shown in the header)

Low Dur

Description

Low Task Duration is used to calculate duration on each iteration for probabilistic analysis. Particular meaning of low duration depends on statistical distribution. For example for normal and lognormal distributions, it can be P1, P5, or P10. Low duration does not affect baseline schedule. See “How to define distribution for Start Time, Cost, and Duration” for details.

Related Fields

Duration Base - baseline

Duration High - baseline


 