Task Related Fields

Duration High - baseline

Name of parameters (shown on the tool tip)

Duration High - baseline

Type of the field

Edit Box with Spin Control

Short name (shown in the header)

High Dur

Description

High Task Duration is used to calculate the duration of each iteration for probabilistic analysis. The particular meaning of high duration depends on statistical distribution. For example for normal and lognormal distributions, it can be P90, P95, or P99. High duration does not affect baseline schedule. See “How to define distribution for Start Time, Cost, and Duration” for details.

Related Fields

Duration Base - baseline

Duration Low - baseline


 